In 2009, Aquawest supplied and installed the complete system to the Department of Water and Energy specifications.

Water is supplied by two Artesion Bores.

Installation Included;

  • 45,000 Metres Pipeline
  • 37 Storage tanks
  • 90 Stock troughs

All trenching was carried out with our RT115 Ditchwitch Trencher with a 600mm cover over pipeline.

Booster pumps at Nardoo were Grundfos CR5.10 with auto timeclock control, pumping from a 154,000 litre Rhino Liner Tank.

Poly Piping was manufactured by Vinidex, tanks were supplied by Clark Tanks and troughs supplied by Yeomans from Walgett.

The system was completed in 12 weeks and the system was supervised during the construction works by our on site foreman with regular meetings with the landholders to insure a quality installation.